Hydrotest & Reinstatement Checklist

Field-oriented checklist for hydrostatic testing of process piping per ASME B31.3 Chapter VI and typical project commissioning procedures.

Before the test

  • Test package approved with marked-up isos and limits
  • Test pressure = 1.5 × design × (Sa/Sd), per Para. 345.4.2
  • All welds visible (no insulation, no painting on welds)
  • Calibrated pressure gauges (range ~1.5–4× test P), dead-weight or master gauge available
  • Test medium quality: potable water, chloride limit for SS (typ. <50 ppm)
  • PSVs, control valves, instruments, orifice plates removed or isolated
  • Vents at high points and drains at low points fitted
  • Temporary supports for water weight verified

During the test

  • Fill from the lowest point, vent all air
  • Pressurise in stages (e.g. 25 / 50 / 100 %), hold and inspect at each stage
  • Hold at test pressure for the specified period (commonly ≥ 10 min, then leak inspection at design pressure)
  • Walk the line; no leaks, no permanent deformation

Reinstatement

  • Drain completely (especially SS — chloride concentration on drying)
  • Reinstall PSVs, control valves, orifice plates, instruments with correct gaskets
  • Torque flanges per project bolting procedure
  • Update test pack, punch list and as-built isos
  • Hand over for N2 purge / dry-out / commissioning

Key references

  • · ASME B31.3 Chapter VI
  • · ASME PCC-2 (repairs)